Yr Hen Ffordd Geffylau, Gilfach Goch
5 House Developement off the High Street in Gilfach Goch. Traditional Build properties with an outstanding finish.
5 House Developement off the High Street in Gilfach Goch. Traditional Build properties with an outstanding finish.
ADDRESS: VIRIDOR WASTE MANAGEMENT, CARDIFF
CLIENT: WESTERN POWER DISTRIBUTION
VALUE: Approx £250,000.00
Construction of a new Switch Room for independent connection by WPD
Specialist Works included
ADDRESS: UNITS 8&9 WATERTON INDUSTRIAL ESTATE
CLIENT: COOPER STANDARD
VALUE: £400,000.00
Refurbishment of Factory and Offices, staff room and Conference Room
ADDRESS: BRODAWEL FARM, COYCHURCH
CLIENT: MR I RAWNSLEY (PRIVATE)
VALUE:
Clear land to rear of the property
Excavate and lay new concrete bases for stables
ADDRESS: CWMBRAN SUBSTATION
CLIENT: WESTERN POWER DISTRIBUTION
VALUE: £80,000.00
Excavate the perimeter of the exiting switch room and apply water proof coating below foundation and up to predicted flood level.
Civil works to GT2 Aux & TX plinth, consisting of new bund walls, & sump construction.
Installation of double flap Non-return Valves.
Construction of flood door reinforced concrete bund.
Installation of pumps and associated drainage works.
Removal/relocation of switch room low level air vents.
Seal duct entries in switch room.
ADDRESS: BRITON FERRY SUBSTATION
CLIENT: WESTERN POWER DISTRIBUTION
VALUE: Approx £490,000.00
Construct compound extension, including the erection of temporary and permanent palisade fence.
Construct new Switch room.
Construct new Access road.
Demolition of existing blast wall and provide new TX plinth
Click on Add Media->Create Gallery to add a gallery
This former brownfield site has been developed to provide 3 No. detached executive style houses that are distinctive, attractive and sustainable meeting the Clients design brief.
The project has been constructed of a highly insulated timber frame with quality in mind and finished to the highest of standards. The internal layouts and design have a contemporary feel with clean lines and finishes, and provides for a high class living environment.
Due to the meticulous standard of workmanship demanded by Manning Construction, it is testament that the air permeability rates of below 4 and SAP values in the high 80s were achieved and are of the highest order.
A good working relationship between the Building Control Surveyor and the Site Agent was maintained throughout the project resulting in a trouble free handover.
ADDRESS: LAND AT FORMER GLANOGWR OFFICES GLANOGWR ROAD BRIDGEND
AGENT: DAVIES EVANS PARTNERSHIP